The Bower House Gallery Renovation
Friday, 14 September 2012
12th Sep - Concrete floors laid!
Poured concrete floors of workshop/ working space
Frazer demonstrating how the surviving wall falls apart by touching!
10th Sep - Drainage
Drainage going in for workshop
7th Sep Foundations
Foundations starting!
Blocks being laid with cavity - we loose 100mm around inside of these rooms due to having to fit in with regulations of a newbuild! Shame.
4th September - Skip day!
A lot of soil and hardcore to remove before foundations go in
Hole being made where doorway through to garden will be
Chimney being re-built! Yey!
Frazer making room for skip
Fireplace revealed in gallery
12 skip loads!